Phase
1 to Save the Covered Bridge When final reconstruction of the bridge is complete, almost
all traces of the temporary cradle will have been removed. The photos
on this and an accompanying page, taken by John Field and Shirley Moon,
will be the primary record of this important step in saving the covered
bridge at Bridgeport. |
A fork lift carries a
column into place for pre-assembly of the south column
pair. |
A cross member is
bolted
at the top of a column. |
Cross member in place. |
Complete X frame at the
top of the column pair. |
A huge crane picks up
the south end column pair to carry it to the bridge. |
Nearly vertical.
The outward splaying at the top is part of the design, not an optical
illusion (see the drawing in Part 1). |
At this point, the
columns are not connected to the X frame at its bottom, |
The spreading is even
more apparent in this photo. |
A bit of the roof had
to be removed as the columns were lowered onto the south piers. |
Workman now has access
to the bottom beam of the X frame. |
Mating the columns to
their piers. |
Continuing the
alignment process. |
A portable come-along was used to pull the column into position, where it was bolted to its pier. |
Tie rods were then
connected to their anchors the next day. |
...from the tops of the
columns. |
Zoomed view from the
modern bridge upstream. |
Similar procedures were
used to install rod anchors and columns at the north end of the bridge. |
Final connections
between the columns, via the intermediate bridge support beams, were
done with high-strength threaded rods, |
Another view of
connections to the north intermediate cross beam. |
Columns and tie rods
along the east side of the bridge. |